Cost estimate: direct costs, overheads, profit and VAT
Build a cost estimate for construction or a refurbishment: direct costs, overheads, profit and VAT, and the cost per square metre.
Or ask in your own words (needs an AI key)
What you need
- direct costs: materials, labour, machinery
- overheads, % of direct costs
- estimated profit, % of direct costs plus overheads
- VAT rate, % (default 20; norm: standard VAT 20% — Tax Code of Ukraine, 193.1)
- area of the object, m² (for the cost per square metre)
What it calculates
- overheads
- estimated profit
- total net of VAT: direct, overheads, profit
- VAT amount
- estimated cost including VAT
- cost per square metre including VAT
Examples
Direct 1,000,000, overheads 15%, profit 8%, VAT 20%, 120 m²
| overheads | 150,000 |
| estimated profit | 92,000 |
| total net of VAT: direct, overheads, profit | 1,242,000 |
| VAT amount | 248,400 |
| estimated cost including VAT | 1,490,400 |
| cost per square metre including VAT | 12,420 |
No area
| overheads | 20,000 |
| estimated profit | 11,000 |
| total net of VAT: direct, overheads, profit | 231,000 |
| VAT amount | 46,200 |
| estimated cost including VAT | 277,200 |
Example numbers are checked against an independent calculation. The AI in Numo does not compute: it only parses your question; a deterministic engine does the maths.
Careful
Simplified: overheads are on all direct costs and profit on direct costs plus overheads. In public-sector estimates the bases and norms for overheads and profit differ (on labour, by norms) — take them from the estimating norms in force and enter ready percentages. No risk allowance or contingency.
Typical mistakes
- Adding VAT on direct costs only: VAT applies to the whole value, including overheads and profit.
- Profit on direct costs only: its base is direct costs together with overheads.
- Comparing a price with and without VAT: a VAT payer recovers it through the input credit.