Capacity, utilisation and staffing

Whether a workshop, kitchen, warehouse or call centre can meet the plan; how many people and shifts the demand needs.

Calculate in Numo

Or ask in your own words (needs an AI key)

What you need

What it calculates

Examples

10 u/h, 5 people, 8 h, 22 days, demand 7,000, 100% efficiency

output possible in the period8,800 units
capacity utilisation by demand79.5455 %
workers needed for the demand3.9773 people
spare capacity (negative — shortfall)1,800 units

Calculate this example →

6 u/h, 12 people, 2 shifts of 7.5 h, 21 days, demand 25,000, 85% efficiency

output possible in the period19,278 units
capacity utilisation by demand129.682 %
workers needed for the demand15.5618 people
spare capacity (negative — shortfall)-5,722 units

Calculate this example →

Example numbers are checked against an independent calculation. The AI in Numo does not compute: it only parses your question; a deterministic engine does the maths.

Careful

Real efficiency is never 100%; above 85% utilisation queues and delays grow sharply (see “Queues”).

Typical mistakes