Capacity, utilisation and staffing
Whether a workshop, kitchen, warehouse or call centre can meet the plan; how many people and shifts the demand needs.
Or ask in your own words (needs an AI key)
What you need
- units per hour per worker (station)
- workers (stations)
- hours per shift
- shifts per day (default 1)
- working days in the period
- demand for the period, units
- real efficiency (breaks, changeovers), % (default 85)
What it calculates
- output possible in the period, units
- capacity utilisation by demand, %
- workers needed for the demand, people
- spare capacity (negative — shortfall), units
Examples
10 u/h, 5 people, 8 h, 22 days, demand 7,000, 100% efficiency
| output possible in the period | 8,800 units |
| capacity utilisation by demand | 79.5455 % |
| workers needed for the demand | 3.9773 people |
| spare capacity (negative — shortfall) | 1,800 units |
6 u/h, 12 people, 2 shifts of 7.5 h, 21 days, demand 25,000, 85% efficiency
| output possible in the period | 19,278 units |
| capacity utilisation by demand | 129.682 % |
| workers needed for the demand | 15.5618 people |
| spare capacity (negative — shortfall) | -5,722 units |
Example numbers are checked against an independent calculation. The AI in Numo does not compute: it only parses your question; a deterministic engine does the maths.
Careful
Real efficiency is never 100%; above 85% utilisation queues and delays grow sharply (see “Queues”).
Typical mistakes
- Planning at 100% capacity — the smallest disruption breaks the plan.
- Confusing workers per shift with total staff: with two shifts you need twice as many people as stations.
More in this family «Operations»
- Product yield: how much to buy to get the usable weight you need
- Driving hours: how long you can still drive before a break, today and this week
- Overall equipment effectiveness (OEE)
- Vehicle loading: how many boxes fit by volume and weight
- Newsvendor
- Economic order quantity
- Baker’s percentages: water, salt and yeast from the flour weight
- Safety stock
- Takt time and number of stations