Home / Methods / Operations / Safety stock
Safety stock
How much extra stock to keep on hand so a delayed delivery doesn't stop you cold.
Or ask in your own words (needs an AI key)
What you need
- spread of demand per period
- delivery lead time, in periods
- target service level, % (default 95)
- average demand per period — needed for the reorder point
What it calculates
- how many extra units to hold as a buffer during the lead time (units)
- how many standard deviations this service level needs
- the stock level at which it's time to reorder more (units), pcs
Examples
Demand SD 20 per period, lead time 4, 95% service, demand 100
| how many extra units to hold as a buffer during the lead time (units) | 65.7941 |
| the stock level at which it's time to reorder more (units) | 465.794 pcs |
Demand SD 15 per period, lead time 2, 99% service, demand 50
| how many extra units to hold as a buffer during the lead time (units) | 49.3493 |
| how many standard deviations this service level needs | 2.3264 |
| the stock level at which it's time to reorder more (units) | 149.349 pcs |
Example numbers are checked against an independent calculation. The AI in Numo does not compute: it only parses your question; a deterministic engine does the maths.
Careful
Raising the service level from 95% to 99% costs disproportionately more — the required stock jumps sharply for a small gain.
Typical mistakes
- Using the maximum demand instead of its spread: safety stock is inflated for nothing.
- Multiplying the spread by the lead time instead of its square root: the stock is overstated, because swings in different periods partly cancel out.
Professions that use it
More in this family «Operations»
- Capacity, utilisation and staffing
- Product yield: how much to buy to get the usable weight you need
- Driving hours: how long you can still drive before a break, today and this week
- Overall equipment effectiveness (OEE)
- Vehicle loading: how many boxes fit by volume and weight
- Newsvendor
- Economic order quantity
- Baker’s percentages: water, salt and yeast from the flour weight