Home / Methods / Management / Critical path (CPM): the shortest project duration, the tasks that cannot slip and the slack of the rest
Critical path (CPM): the shortest project duration, the tasks that cannot slip and the slack of the rest
A plan of tasks that depend on each other (renovation, product launch, construction, an event): how long the whole project takes at the very least, which tasks are “critical” — any delay to them moves the end — and how much the rest can slip.
What you need
- tasks separated by semicolons: “name duration after predecessors”, e.g. “A 5; B 3 after A; C 4 after A; D 2 after B, C” (durations in the same unit: days or weeks)
- deadline — how many time units you have (optional)
What it calculates
- shortest possible project duration (in the same units as the tasks)
- tasks in the plan, pcs
- tasks on the critical path (any delay to them moves the whole project), pcs
- largest slack among non-critical tasks (how much it can slip without moving the end)
- buffer to the deadline (negative — we will be late)
Examples
A 5 days; B 3 after A; C 4 after A; D 2 after B and C
| shortest possible project duration (in the same units as the tasks) | 11 |
| tasks in the plan | 4 pcs |
| tasks on the critical path (any delay to them moves the whole project) | 3 pcs |
| largest slack among non-critical tasks (how much it can slip without moving the end) | 1 |
Renovation: demolition 3 days; wiring 5 and plumbing 4 after demolition; plaster 6 after both; flooring 4 and painting 3 after plaster; furniture 2 after flooring and painting; deadline 25 days
| shortest possible project duration (in the same units as the tasks) | 20 |
| tasks in the plan | 7 pcs |
| tasks on the critical path (any delay to them moves the whole project) | 5 pcs |
| largest slack among non-critical tasks (how much it can slip without moving the end) | 1 |
| buffer to the deadline (negative — we will be late) | 5 |
Example numbers are checked against an independent calculation. The AI in Numo does not compute: it only parses your question; a deterministic engine does the maths.
Careful
The critical path method treats durations as exact and resources as unlimited: if the same person does two tasks, they really run one after another and the project is longer. For uncertain durations use the three-point estimate (PERT). The only dependency here is “start after the previous one finishes”.
Typical mistakes
- Adding up all task durations: parallel tasks run at the same time, and the duration is set by the longest chain, not the sum.
- Speeding up a non-critical task: the project end does not move — it is the critical path that has to be shortened.
- Forgetting that slack is shared: once a non-critical task uses up its slack, another chain can become critical.