Home / Methods / Management / Three-point project estimate (PERT)
Three-point project estimate (PERT)
How long a project, renovation or development will really take — and the chance of making the date.
What you need
- optimistic (for each stage in order)
- most likely
- pessimistic
- deadline in the same units
What it calculates
- expected duration
- spread (standard deviation)
- duration you will not exceed with 90% probability
- probability of meeting the deadline, %
Examples
One stage 4 / 6 / 14 days, deadline 9
| expected duration | 7 |
| spread (standard deviation) | 1.6667 |
| probability of meeting the deadline | 88.493 % |
Three stages: 2 / 4 / 8, 5 / 8 / 15 and 1 / 2 / 6 days, deadline 20
| expected duration | 15.5 |
| spread (standard deviation) | 2.1148 |
| duration you will not exceed with 90% probability | 18.2102 |
| probability of meeting the deadline | 98.3327 % |
Example numbers are checked against an independent calculation. The AI in Numo does not compute: it only parses your question; a deterministic engine does the maths.
Careful
Stages are sequential and independent; parallel branches and shared risks (the same contractor on every stage) widen the spread.
Typical mistakes
- Planning on the “most likely” durations: their sum is almost always shorter than reality.
- Adding the stages’ standard deviations directly instead of their variances: for independent stages the project spread is overstated.