Three-point project estimate (PERT)

How long a project, renovation or development will really take — and the chance of making the date.

Calculate in Numo

What you need

What it calculates

Examples

One stage 4 / 6 / 14 days, deadline 9

expected duration7
spread (standard deviation)1.6667
probability of meeting the deadline88.493 %

Calculate this example →

Three stages: 2 / 4 / 8, 5 / 8 / 15 and 1 / 2 / 6 days, deadline 20

expected duration15.5
spread (standard deviation)2.1148
duration you will not exceed with 90% probability18.2102
probability of meeting the deadline98.3327 %

Calculate this example →

Example numbers are checked against an independent calculation. The AI in Numo does not compute: it only parses your question; a deterministic engine does the maths.

Careful

Stages are sequential and independent; parallel branches and shared risks (the same contractor on every stage) widen the spread.

Typical mistakes