Earned value (EVM): is the project on budget and on schedule, what will it really cost

A project in progress (construction, renovation, IT, a roll-out): compare what should have been done, what was done and what was spent. It shows whether you are on budget and on schedule, and what the project will cost if things go on like this.

Calculate in Numo

Or ask in your own words (needs an AI key)

What you need

What it calculates

Examples

Budget 1,000,000; work worth 400,000 should have been done by today, 350,000 was done, 420,000 spent; a 10-month project

earned value EV — budgeted cost of the work done350,000
cost variance CV = EV − AC (negative — over budget)-70,000
schedule variance SV = EV − PV (negative — behind schedule)-50,000
cost performance index CPI = EV ÷ AC: work gained per unit spent (below 1 — over budget)0.8333
schedule performance index SPI = EV ÷ PV: share of the planned work done (below 1 — behind)0.875
estimate at completion EAC = BAC ÷ CPI (if the spending rate holds)1,200,000
estimate to complete ETC = EAC − AC780,000
variance at completion VAC = BAC − EAC (negative — overrun)-200,000
to-complete performance index TCPI: work per unit needed from now on to stay within budget1.1207
share of the work done35 %
share of the budget spent42 %
forecast duration at the current pace = plan ÷ SPI11.4286 mo

Calculate this example →

Renovation: budget 500,000, planned 250,000, 60% of the work done, 240,000 spent

earned value EV — budgeted cost of the work done300,000
cost variance CV = EV − AC (negative — over budget)60,000
schedule variance SV = EV − PV (negative — behind schedule)50,000
cost performance index CPI = EV ÷ AC: work gained per unit spent (below 1 — over budget)1.25
schedule performance index SPI = EV ÷ PV: share of the planned work done (below 1 — behind)1.2
estimate at completion EAC = BAC ÷ CPI (if the spending rate holds)400,000
estimate to complete ETC = EAC − AC160,000
variance at completion VAC = BAC − EAC (negative — overrun)100,000
to-complete performance index TCPI: work per unit needed from now on to stay within budget0.7692
share of the work done60 %
share of the budget spent48 %

Calculate this example →

Example numbers are checked against an independent calculation. The AI in Numo does not compute: it only parses your question; a deterministic engine does the maths.

Careful

The forecast EAC = BAC ÷ CPI assumes cost efficiency stays the same; if the overrun was a one-off, the real cost is closer to AC + (BAC − EV). Near the end SPI always drifts to 1 even if the deadline is missed — so the schedule forecast is reliable only mid-project. Everything depends on an honest estimate of the work done (EV): “almost done” without measurable results makes the indices look better than they are. PMI standard method (PMBOK).