Home / Methods / Management / Earned value (EVM): is the project on budget and on schedule, what will it really cost
Earned value (EVM): is the project on budget and on schedule, what will it really cost
A project in progress (construction, renovation, IT, a roll-out): compare what should have been done, what was done and what was spent. It shows whether you are on budget and on schedule, and what the project will cost if things go on like this.
Or ask in your own words (needs an AI key)
What you need
- budget of the whole project, BAC (Budget at Completion — the planned cost of the whole project)
- planned value to date, PV (Planned Value — how much budgeted work should have been done by today on schedule)
- earned value, EV (Earned Value — what the work actually done is worth at budget prices)
- share of all work done, % — if you do not know EV (then EV = BAC × %)
- actual cost to date, AC (Actual Cost — how much has really been spent)
- planned project duration, months — for a schedule forecast (optional)
What it calculates
- earned value EV — budgeted cost of the work done
- cost variance CV = EV − AC (negative — over budget)
- schedule variance SV = EV − PV (negative — behind schedule)
- cost performance index CPI = EV ÷ AC: work gained per unit spent (below 1 — over budget)
- schedule performance index SPI = EV ÷ PV: share of the planned work done (below 1 — behind)
- estimate at completion EAC = BAC ÷ CPI (if the spending rate holds)
- estimate to complete ETC = EAC − AC
- variance at completion VAC = BAC − EAC (negative — overrun)
- to-complete performance index TCPI: work per unit needed from now on to stay within budget
- share of the work done, %
- share of the budget spent, %
- forecast duration at the current pace = plan ÷ SPI, mo
Examples
Budget 1,000,000; work worth 400,000 should have been done by today, 350,000 was done, 420,000 spent; a 10-month project
| earned value EV — budgeted cost of the work done | 350,000 |
| cost variance CV = EV − AC (negative — over budget) | -70,000 |
| schedule variance SV = EV − PV (negative — behind schedule) | -50,000 |
| cost performance index CPI = EV ÷ AC: work gained per unit spent (below 1 — over budget) | 0.8333 |
| schedule performance index SPI = EV ÷ PV: share of the planned work done (below 1 — behind) | 0.875 |
| estimate at completion EAC = BAC ÷ CPI (if the spending rate holds) | 1,200,000 |
| estimate to complete ETC = EAC − AC | 780,000 |
| variance at completion VAC = BAC − EAC (negative — overrun) | -200,000 |
| to-complete performance index TCPI: work per unit needed from now on to stay within budget | 1.1207 |
| share of the work done | 35 % |
| share of the budget spent | 42 % |
| forecast duration at the current pace = plan ÷ SPI | 11.4286 mo |
Renovation: budget 500,000, planned 250,000, 60% of the work done, 240,000 spent
| earned value EV — budgeted cost of the work done | 300,000 |
| cost variance CV = EV − AC (negative — over budget) | 60,000 |
| schedule variance SV = EV − PV (negative — behind schedule) | 50,000 |
| cost performance index CPI = EV ÷ AC: work gained per unit spent (below 1 — over budget) | 1.25 |
| schedule performance index SPI = EV ÷ PV: share of the planned work done (below 1 — behind) | 1.2 |
| estimate at completion EAC = BAC ÷ CPI (if the spending rate holds) | 400,000 |
| estimate to complete ETC = EAC − AC | 160,000 |
| variance at completion VAC = BAC − EAC (negative — overrun) | 100,000 |
| to-complete performance index TCPI: work per unit needed from now on to stay within budget | 0.7692 |
| share of the work done | 60 % |
| share of the budget spent | 48 % |
Example numbers are checked against an independent calculation. The AI in Numo does not compute: it only parses your question; a deterministic engine does the maths.
Careful
The forecast EAC = BAC ÷ CPI assumes cost efficiency stays the same; if the overrun was a one-off, the real cost is closer to AC + (BAC − EV). Near the end SPI always drifts to 1 even if the deadline is missed — so the schedule forecast is reliable only mid-project. Everything depends on an honest estimate of the work done (EV): “almost done” without measurable results makes the indices look better than they are. PMI standard method (PMBOK).
Typical mistakes
- Comparing only spending with the plan (AC with PV) without earned value: “spent less than planned” can mean savings or simply that the work was not done.
- Taking EV as the share of money spent rather than work done: then CPI is always 1 and overruns are invisible.
- Taking planned value (PV) at the end of the project instead of today: the delay will look bigger.